Asian Development Bank spells out reasons for 2015-2016 country-wide blackout

The Asian Development Bank has set out a series of reasons that attributed to country-wide black-outs within a span of 07 months from 2015 to 2016.

According to the Asian Development Bank, poor operation of the protection system, lack of operational flexibility and bottlenecks in the transmission system attributed to the country-wide blackouts.

The Asian Development Bank listed under-investment in the transmission and medium voltage network and protection system resulting from high government debt to GDP ratio and poor financial status of the Ceylon Electricity Board as other reasons for higher generation costs.

The ADB confirmed in an announcement that it will grant 1.5 million USD to Sri Lanka to hire two consulting firms to study and improve the soundness of the island’s power transmission system which has suffered blackouts owing to poor reliability.

This project will start in March 2018 and be completed by February 2019

Asian Development Bank spells out reasons for 2015-2016 country-wide blackout


ගෙවල් හදන්න සිමෙන්ති එපා – මොරටුව සරසවියෙන් විස්මිත සොයාගැනීමක්

??? ?? ??? ??? ?????? ??? ???? ?????? ?????? ??? ?????? ?? ??? ???? ????????. ???????, ????? ???? ????? ?????? ?????? ??? ??? ???????????? ????????????, ?????????? ????. ????? ?? ?? ??? ?????? ??? ???? ????? ??????? ?????? ?????. ?????? ???????? ??? ??? ???? ??????, ????? ??? ?????? ????? ???? ????? ????????? ??????? ??????? ????.

??? ????? ??? ???????? ??? ???? ?????? ?????? ????? ?????? ???????? ?????? ??? ?? ???????? ???? ???? ??????. ??? ?? ??????? ????? ???????? ????? ????? ?????? ????? ???????? ????. ?? ????? ???????? ??????? ??? ?????? ???? ???? ????? ?????? ??? ?????? ??? ??? ????????? ????? ????? ???????. ?? ???????? ???? ?????? ???? ???????? ?????, ????? ?????? ????????? ????? ???? ??? ???? ??? ????????? ????? ?????? ??????????? ?????? ??????????????? ??????? ????????? ??????? ????.

http://www.lakbima.lk/index.php/%E0%B7%80%E0%B7%92%E0%B6%B8%E0%B7%83%E0%B7%94%E0%B6%B8/8679-%E0%B6%9C%E0%B7%99%E0%B7%80%E0%B6%BD%E0%B7%8A-%E0%B7%84%E0%B6%AF%E0%B6%B1%E0%B7%8A%E0%B6%B1-%E0%B7%83%E0%B7%92%E0%B6%B8%E0%B7%99%E0%B6%B1%E0%B7%8A%E0%B6%AD%E0%B7%92-%E0%B6%91%E0%B6%B4%E0%B7%8F

?????? ???, ????? ??????? ??? ????? ???????, ??????????? ??? ????? ???????? ??????? ???? ?????? ??? ??? ????????? ???????? ???????? ?????? ???? ?? ??? ??????? ???????. ??????????? ??????? ??????? ????????? ???? 4? ??? ??? ?????? ??????????? ????? ??????? ???? ??????. ??? ???????? ??????? ????????. ????? ? ????? ????????    ????????? ?? ???? ??? ?? ???????? ?????? ????? ?????? ???????? ??????? ????? ??????????. ??? ??????????? ??????????? ????? ??? ?????????? ???? ?? ?????? ???. ??? ??????? ??????? ????? ????? ???? ???? ????????? ???? ?????. ?? ?????? ?? ????? ????? ???? ??? ????????? ????? ????.

????? ???????? ???????? ??? ?? ?????? ???????? ?? ?????? ????? ??????? 517???? ???? 50???? ??????? ???? ???????? ??????? ???????? ??????? ??????. ?? ??????? ???? ????? ?????? ???????? ?????? ??????? ??????????? ?????????? ??????. ??? ????? ???? ????? ??? ????? ?????? ??? ??????? ?????? ??????? ??????? ???? ????. ? ???? ??????? ?????????? ?????? ??????, ???????? ?????????? ?? ????? ????? ??? ?????, ?????? ???????? ??? ??? ????????? ??????, ??????? ??? ?????? ?????, ?????? ?????????? ??? ????? ??????? ??? ?????, ?? ?????? ?????? ??????? ???????? ?????? ???? ?????? ??????? ?????? ????? ?? ???? ?? ??????? ????.

??????? ?????????? ??????? ???????? ???? ?? ??? ??????? ??????? ????? ????? ??? ??????? ???????? ??? ?????????? ???? ????? ???????? ??????? ?? ?? ??????? ???? ?????? ?????? ??????.

?? ????? ????? ??????? ?????. ????????? ?????? ??????????? ?????? ??? ??? ??? ???????? ???? ?? ????. ??????? ???????? ?????????????? ??? ???????? ???????? ???????? ?????? ??? ???? ????. ? ???? ?? ?????? ??? ????? ??????? ?? ?? ??????? ???? ??????? ?????? ???????? ?????. ?? ??????? ?????? ???????? ?????? ???? ?????? ??????.

???????? ??????????? ???? ??? ????? ???????? ??? ????????? ?????? ???????? ?? ????????? ??? ?? ??????????????? ??????? ??????. ? ???? ?? ?????? ?????? ??? ????? ??? ????, ??? ?????, ??? ???? ????? ????? ????? ???????? ??? ?????? ??? ??????? ????? ????? ?????? ????. ????? ?????? ????? ???? ???????? ??? ??????? ???? ?????? ????? ????? ?????? ?? ??.

?????? ??? ?? ??????????? ??? ????? ?? ???????? ?????? ??????? ????? ?????? ?? ?????? ???????? ????? ??? ???? ?????? ??????? ?????. ???? ????? ?? ?????? ??????? ??????? ????? ??????? ????? ?????? ??? ??????? ????? ????? ????? ??????? ?????? ???????? ???????? ???????? ??????????? ??? ?????? ??????? ???? ????? ???????????.

???????? ???????? ???????? ????? ??????? ???? ????? ?????? ??????. ????? ???????? ???????? ??????????? ??? ?????? ????? ??? ??? ?? ???????? ????? ????????? ??????? ?????? ???? ???? ???? ?????? ?? ????? ????? ?????? ?????? ?????? ??????? ???. ?????? ?????????? ??? ???????? ??? ????????????? ??? ?????? ????? ??????. ??? ?????? ???????? ??? ????? ??????? ??????? ??? ??? ????????

?????? ??????? ???? ????? ???????. ????? ??? ?? ???? ????? ??? ??????? ?? ????? ?????? ????? ???? ????? ???? ????????? ????????? ?? ?????? ???? ????? ?????? ??????? ???? ???? ??? ??.

???????? ???? ????? ??? ?????????? ?????. ????? ???? ?? ????????? ???? ??? ??? ??? ????????? ??? ????? ?? ????? ???????? ?????. ??? ???? ?? ??????? ????? ?????? ??? ??? ????????? ???, ?????? ???????? ????? ?? ????????? ??????? ????? ??????? ??? ???? ??????? ??????? ????????? ???????. ??? ?? ??????????? ????? ???????? ??????? ????? ??????? ????? ?????? ??? ????? ?????? ??? ?????? ???? ??? ???? ??????? ????? ??????? ??????. ??????? ???? ?????? ????? ???????.

????? ?????, ????? ????? ??? ???? ????? ?????? ??????????? ??????? ???? ???? ??????? ???????? ????? ??? ???. ? ???? ????? ?? ????? ???? ???? ????? ??? ???? ????, ???? ???? ????, ???? ??? ????? ???????? ?????? ???? ?? ????. ???? ??????? ????? ???????? ??????? ?? ???? ?????? ?????? ????? ???????? ????? ??????. ????? ????? ????? ??? ????????????? ????? ????? ??????? ?? ?? ????. ??????? ??? ????

??????????? ?????? ????????????? ??? ??????? ?????. ??? ???????? ???? ????????? ??? ?????? ??????????????? ???????? ????? ????????? ?????????? ?? ?? ??????? ???? ???????, ?????? ???????? ???? ?????? ??? ?????????? ?????? ????? ???????? ???????? ?????? ?????195?? ?????? ???????? ?? ?????? ????? ??????? 517???? 2017 ?????? ???? ??????? ???????50 ???? ???? ?????? ????? ????????? ?????? ????? ???????? ??????. ?????? ??? ??? ?????????????? ???? ??? ???????? ????????? ????? ?? ?? ??????????? ?????????? ?????? ???? ???? ??????????? ??? ??? ??????? ??????? ???? ???? ??? ????? ????? ?? ??????? ????.

විදුලි අර්බුදයට රජයට වැඩපිළිවෙළක් නෑ – විදුලිබල ඉංජිනේරු සංගමය

???????? ??????? ????? ?????? ???????? ???????? ???? ???? ?????? ???????????? ?????? ???????? ???????? ????? ????? ????.

?????? ???? ????? ????? ??????? ??????? ???? ???? 100? ?????????? ?????? ?? ????, ?????? ?????? ???? ?????????? ???????? ??? ?????????? ???? ?????? ??????? ?? ????? ?????? ? ???? ???????? 300?? ????? ???? ?????? ??? ?? ?????? ????? ??????? ???????? ???? ??????????? ???? ????? ????.

powerlines-ac-power-transmission-348x196

?????? ????? ?????? ???? ???? 100? ???????? ????? ?????? ????? ?????? ???? ????? ?????? ??????? ???, ?????????? ?????? ??? ???????? ???????? ???????? ???? ???????? ?????? ??????? ??????????? ?????? ???? ??? ??? ???? ???????.

??? ?????? ??????? ?????? ???? ?? ????? 2018 ??? 2037 ????? ??? ????????? ???? ?? ????, ????? ?????? ?? ????????? ?? ?????? ?????? ??? ???? ? ???? ????? ????.

??? ??????? ???????????????? ???? 2013 ?????? ??? ?????? ????????? ????????? ?????? ?? ????? ????, ???????? ??? ???? ?????????? ????? ????? ?????? ???? ??????? ???????? ??? ????? ????? ?? ????? ???? ???? ??????????? ???? ??????? ????.

?? ?????? %??^ ???????? ??????? ?????? ???????? ??????? ??????? ???????? ?? ????????? ?????? ???????????? ????? ???, ?????? ???? ????? ????? ????????? ??????????? ??? ???????? ???? ????? ?????? ????? ?????? ????? ?? ????? ????.

?? ???? ??????? ????? ?? ???????? ??????? ???????? ?? ????? ????, ?????????? ???????? ?????? ?????? ???? ???????? ??????? ??? ?????? ?????????? ???? ???? ????? ?? ???? ??? ???? ???????.

????? ????????? ??? ???? ?????? ??????? ??????? ?????? ?????? ??? ????, ?????? ??????? ???????????? ????? ?? ???? ???? ????? ????? ????.

http://www.ada.lk/article/303453/%E0%B7%80%E0%B7%92%E0%B6%AF%E0%B7%94%E0%B6%BD%E0%B7%92-%E0%B6%85%E0%B6%BB%E0%B7%8A%E0%B6%B6%E0%B7%94%E0%B6%AF%E0%B6%BA%E0%B6%A7-%E0%B6%BB%E0%B6%A2%E0%B6%BA%E0%B6%A7-%E0%B7%80%E0%B7%90%E0%B6%A9%E0%B6%B4%E0%B7%92%E0%B7%85%E0%B7%92%E0%B7%80%E0%B7%99%E0%B7%85%E0%B6%9A%E0%B7%8A-%E0%B6%B1%E0%B7%91—%E0%B7%80%E0%B7%92%E0%B6%AF%E0%B7%94%E0%B6%BD%E0%B7%92%E0%B6%B6%E0%B6%BD-%E0%B6%89%E0%B6%82%E0%B6%A2%E0%B7%92%E0%B6%B1%E0%B7%9A%E0%B6%BB%E0%B7%94-%E0%B7%83%E0%B6%82%E0%B6%9C%E0%B6%B8%E0%B6%BA

FSRU Plant Govt, Japan and India in joint venture Officials decry move

By Niranjala Ariyawansha

Ceylon Today

The Government has decided to go for a joint venture with India and Japan towards the setting up of a Floating Storage Regasification Unit (FSRU), which would convert diesel plants to LNG, for a sum of US $300 million, despite opposition from top officials.

The Cabinet Committee on Economic Management (CCEM), which has forwarded this proposal, has not included any environment or final feasibility report with it.

With the country being devoid of any energy plan or policy, it would be dangerous to release the country’s power sector in an ad hoc manner to overseas buyers, these officials charged.

Sources said the Government has decided to implement this joint venture, although Australia had earlier submitted a proposal to set up an FSRU for half of that sum.

Also, South Korea, under an agreement that Sri Lanka has to purchase LNG from Seoul for over a 25-year period, had even consented to set up a FRSU free-of-charge.

However, having put aside the proposals from South Korea and Australia, the Government is now preparing to opt for the joint venture by the end of this month with the four firms that are to be submitted by the three countries, a top official from a Ministry told Ceylon Today.

The firms are Sri Lanka Gas Company, which comes under the Treasury, Petromat Oil & Gas Equipment (Pvt) Ltd of India and Sojitz & Mitsubishi for Japan are those companies.

As per the joint venture, these firms are set to import gas to Colombo over a 20-year period.

The Ceylon Petroleum Corporation (CPC) will function as a Single Credible Entity towards the gas imports.

According to this plan, the lowest percentage of shares (15) will be left to Sri Lanka, 47.5 per cent will go to India, while 37.5 shares will be given to Japan.

A top official stated that they had to fight tooth and nail to hold on to the 15 per cent.

The Ceylon Electricity Board (CPC) has already expressed opposition to this joint venture. Ministers Ranjith Siyambalapituya and Dr. Sarath Amunugama having submitted a Cabinet Paper a fortnight ago, noted that they have decided to import gas in a bid to convert the diesel plants owned by the CEB to LNG.

Furthermore it has also been mentioned in the agreement that Colombo will be going for a joint venture with New Delhi regarding the China Bay Oil Tank Farm in Trincomalee.

The proposal which was submitted to the Cabinet, prior to Prime Minister Ranil Wickremesinghe’s visit to India in April last year, had also been ratified.

“The CCEM is taking decisions regarding the country. They think that Government officials, by forwarding various circulars, are placing burdens on the country’s development drive. But we do that not with the aim of scuttling development programmes but towards the betterment of the country. These circulars have been made to prevent both politicians and their henchmen from damaging the country by taking arbitrary decisions. However, these decisions can only help to stall the forward march of the country,” a top official said.

He further charged that behind such unsolicited proposals, invariably there are commissions.

The CPC, the Engineers Union of the CEB (CEBEU) and many other trade unions have already protested to this proposal.

CEBEU Committee Member Athula Wanniarachchi said: “There is no energy plan to the country. Instead there is only a business plan. The country’s energy plan is being designed according to the business plan of their friends and kith and kin,” he charged.

The FSRU is set to be established at the Colombo Port. The Convener of the CPC Trade Union Collective Janaka Rajakaruna alleged that due to the threat posed by the setting up of FSRU in a commercial port, the rest of the shipping firms would automatically seek to increase insurance charges.

http://www.ceylontoday.lk/print20170401CT20170630.php?id=38503

Energy expert highlights loopholes in subsidized solar power promo campaigns

The households that have installed solar power panels and are supplying a net excess of electricity to the national grid under the government subsidized solar promotion programmes are placing further burdens on those who do not generate solar power, according to a leading expert.

“When a customer makes his bill zero through net metering or net plus or net accounting or whatever, when his bill is zero, he pays, theoretically, at least a retail service cost,” RMA Consultants Managing Director Dr. Tilak Siyambalapitiya said. However, this does not happen, reducing revenue for the state-run utilities companies and potentially placing such costs among the rest of the households, which do not supply such an excess of electricity to the grid and reduce their bills to zero.

The total cost not charged from solar PV households has increased from Rs.12 million in 2012 to Rs.1 billion by 2016 and is increasing further, according to Dr. Siyambalapitiya, who spoke at the public consultation on rooftop solar PV, organised by the Public Utilities Commission of Sri Lanka (PUCSL).

“So what happens today? A customer who doesn’t have a solar PV system or a customer who can’t afford a solar PV system or a customer who doesn’t have a roof to mount his solar PV system,

is paying the capacity charge of the net metered and net plus and other customers and so on,” he said.

The government is providing subsidies for households to install solar panels, in order to minimize the country going into a power crisis before the year 2020, when the first of the many delayed major power plants are expected to become operational. Environmentally-friendly agendas are also present, which were furthered under the 2018 budget.

Dr. Siyambalapitiya however said that the promotional subsidies provided to induce households to purchase solar PV systems have been going on for around a decade, which is not present in other businesses.

He said that the Christmas promotions currently going on for other businesses will end in a month or so, when such businesses revert to normal operations.
“So promotion is going on, no harm, as long as somebody pays for the promotion. Governments can decide to provide subsidies. But what I say is that not to ignore this developing problem, in which utilities are asked to forgo the distribution revenue due to them by the customers and not defining who pays this,” he said.
The government has committed to also charge cost-reflective electricity prices from consumers next year

The grid is also experiencing higher voltage than it could handle due to solar power directly being supplied to the grid, many experts highlighted at the public consultation, which Dr. Siyambalapitiya too acknowledged.

He said that the PUCSL should not focus only on the good side of household solar power generation but do a complete assessment on the effects of longer-term proliferation of solar PV among households.“Because if you miss certain things, it may be possible that sometime in the near future, the entire programme will be suspended or it may be suspended for review and it may never be started again,” he said.Dr. Siyambalapitiya took responsibility for writing a concept paper in 2008, which resulted in the government approving the net metering concept.

“I had very few supporters then but today also when I express caution, my supporters in 2008 are now against me,” he said.

http://www.dailymirror.lk/article/Energy-expert-highlights-loopholes-in-subsidized-solar-power-promo-campaigns–142228.html

විදුලිය කප්පාදු කිරීමේ අවදානමක් – Hiru News

www.hirunews.lk

??? ?????? ?? ???????? ??????? ?????? ???? ??? ?????????? ?????? ?????????? ?????????? ???????? ????? ?? ???? ???????? ?????? ??????.

?? ???????? ??? ?????????? ?????? ???????? ????????? ??? 45? ?????? ????????? ? ???? ??? ?? ?????.

?????? ????? ?????? ???????? ???????? ??? ???????? 100? ?????? ?????????? ???? ???? ???????? ?????? ????? ??? ???????.

????? ??? ???????? ???????? ????????? ?????? ???????? ????? ?????? ????? ???????? ?? ?????? ??????????? ?????? ?????????? ?????? ??? ????? ?? ??? ?? ?????.

??? ?????? ?? ???????? ???????? ??? ?????? ?????? ??????? ???? ????? ?????????? ????? ?????? ????????? ????? ?? ?????? ??????? ?????????????? ? ??????? ?????.

?? ???? ??????? ?????????????? ????? ??? ????? ???????? ?? ?????????? ??????? ???????????? ?????? ???????? ??????? ??????? ?????? ???????????????? ????? ??????.

http://www.hirunews.lk/sinhala/180962/%E0%B7%80%E0%B7%92%E0%B6%AF%E0%B7%94%E0%B6%BD%E0%B7%92%E0%B6%BA-%E0%B6%9A%E0%B6%B4%E0%B7%8A%E0%B6%B4%E0%B7%8F%E0%B6%AF%E0%B7%94-%E0%B6%9A%E0%B7%92%E0%B6%BB%E0%B7%93%E0%B6%B8%E0%B7%9A-%E0%B6%85%E0%B7%80%E0%B6%AF%E0%B7%8F%E0%B6%B1%E0%B6%B8%E0%B6%9A%E0%B7%8A

ඉදිරි මාර්තු අප්‍රේල් කාලයේ විදුලිය කැපීමේ අවදානමක්!

??? ?????? – ???????? ??????? ??????? ??????? ?????? ????????? ???? ?????? ?? ?????? ????? ?? ????? ?? ?????? ??.

??? ???????? ???? ?? ????? ?? ???? ??? ????????? ?????? ???????? ?????????? ??? 45? ?????? ?????? ???????? ??????? ???????, ???????? 160?? ??? ????? ?????????? ???????? ?????? ???????? ????? ?????????????? ??????, ???????? ???????? 100? ?????? ?? ???????? ?????? ?? ???????? 100? ????? ??? ?? ??????? ???? ?? ?????? ??????? ?? ???? ?? ?????? ??????? ????? ?? ???? ?????? ?? ??????? ?????? ???????? ?????? ?????? ?????? ???????? ???? ???.

????? ???????? ???????? ??? ???????? 100? ????? ?????? ????? ??????? ???? ???? ?????? ?? ?????? ????? ??? ???? ??? ???????? ???????? ????????? ?????? ???????? ????? ?????? ?? ????? ? ??? ???.

????? ????? ?????? ??? ????????? ??????? ??? ???? 2015 ???? ???? ??? ?????? ?????? ????? ??? ?? ?????? ????? ???????? ?????? ??? ?????? ????? ???????? ?????? ????? ?????? ??????????? ?????? ???? ???? ???????? ???????? ?????? ?????? ????? ????? ??? ??? ??????? ????.

Stakeholders perturbed over delay in awarding bid for proposed Kerawalapitiya – II power project

  The Island

Energy sector stakeholders last week expressed concern over the inordinate delay in awarding the bid for the proposed multi-billion rupee 300MW Kerawalapitiya – II Power Plant.

Proposals were opened in April 2017 and though eight months have lapsed, there is still no forward movement, they said. “The fast track project has become an off track one, and the delay has already resulted in a loss of Rs. 12.4 billion”.

Earlier, fears were expressed that the proposed power project was to be awarded to a foreign company, which could have translated into a loss of a staggering Rs. 204 billion as bidders offering more competitive tariffs were apparently sidelined.

The matter was brought to the notice of the President and the Prime Minister, they said, as, if the bid was pushed through, the loss would have been much bigger than the bond scam.

Senior CEB engineers also expressed their reservations about awarding the bid to the Korean company as the margin between the lowest and second lowest bidders worked out to a stupendous Rs. 34 billion, they said

Sri Lanka trying to outsource LNG purchases to one company for 20-years: report

ECONOMYNEXT – Sri Lanka’s current administration is attempting to give a deal to purchase up to a million tonnes of liquefied natural gas a year for 20 years to state-run Ceylon Electricity Board in the guise of building an LNG terminal, a media report said.

http://economynext.com/Sri_Lanka_trying_to_outsource_LNG_purchases_to_one_company_for_20_years__report-3-9569.html

An unsolicited bid by SK E&S Company, which is backed by the government of Korea had been first submitted to President Maithripala Sirisena, Sri Lanka’s The Sunday Times newspaper reported.

Sirisena had already shot down a plan to build a 500MW coal plant which would have given cheaper power to the country, in place of building more expensive LNG plants. LNG plants however are cleaner.

A joint memo has been put to the cabinet of ministers by Energy Minister Ranjith Siyambalapitiya and Special Assignments Minister Sarath Amunugama to get the state-run Ceylon Electricity Board to tender the project on a ‘Swiss Challenge’ concept.

A ‘Swiss Challenge’ will allows another company to better the proposal.

SK E&S Company was offering to supply one million tonnes of LNG on a ‘take or pay’ basis if where the buyer has to pay a penalty if the buyer not accept a shipment, the news report said.

The company will build its own terminal ‘free of charge’ if it gets the contract to supply LNG. But the government will also have to build pipelines for the company.

The price of the LNG, or what premium to what international benchmark was not given in the report. The company has sought a purchase and supply agreement from mid-2020 to March 31, 2040.

Sri Lanka’s government has problems in procurement allegedly paying above market prices. The ousted Rajapaksa administration was faulted for setting up Lanka Coal, which carried out coal procurement outside the purview of the CEB.

Critics also allege hat the administration bought Litro Gas, the country’s largest cooking gas distributor from Shell for political appointees to make money off inflated LPG tenders.

The CEB was originally expected to build its own terminal to unload LNG – or call bids for a private or floating plant which will then charge a throughput fee for each tonne unloaded.

A private operator is expected to build a dual fuel 300MW combined cycle power plant for the CEB, and existing combined cycles could also potentially be converted to run on LNG at an unknown cost.

The proposal to cabinet indicates LNG procurements for plants of up to 1000MW, the report said.

The report said there were several other proposals including an Indian Japan consortium which may be asked to join the ‘Swill Challenge’ process.

Sri Lanka now has several private power plants which were built on competitive tender based on the efficiency of generation (heat rate) with the CEB supplying fuel except for the LakVijaya plant by Lanka Transformers group which was negotiated without a guaranteed heat rate.

There has been concern among energy analysts that several LNG plants have been proposed not on the heat rate but on fuel procurement basis. Sri Lanka does not yet have daily auctions for energy procurement. (Colombo/Jan13/2018)

ලක්විජය බලාගාරයේ ගල් අඟුරු අංගණය හා අළු අංගණය වටා සුළං ආවරණයක් ඉදි කිරීම

??????? ????? ???? 2018.01.09

??????? ???????? ??? ????? ????? ?? ??? ????? ??? ???? ??????? ??? ?????

???????, ??????? ???????? ?????? ??? ?????? ???? ???????? ??? ????? ????????? ???? ?????? 2.4?? ??? ?????? ??. ??? ?????? ?????? ??? ???? ??? ??? ????? ???? ????? ??? ????????? ???????? ????? ???? ?? ?????????, ???? ??? ?? ??? ????? ??? ????????? ???? ?? ????????? ?????? ???? ??. ??? ? ??? ????????????? ????? ???????? ????. ??? ????? ???? ?? ??? ?????? ?????? ?????? ???? 450?? ??? ?? ???? 15?? ?? ???? ??????? ??????? ??? ??? ??? ?????, ?? ???? ??? ??????? ??? ????? ?????????? ???? ?? ????? ??? ??? ????. ??????, ???? ??? ?? ??? ????? ??? ???? ?? ??? ?????? ????? ?? ????? ??? ???? ????? ????? ?????? ????????? ???????? ??? ????.

???????, ??????? ???????? ??????? ???? ????? ??? ????? ????? ?? ??? ????? ? ????????????? ????? ?? ????? ?????? ?? ??? ????? ???? ????????????????? ???? ????? ????? ???? ?????? ??? ????. ? ????, ?? ??????????????, ??????? ?????? ?????? ??? ??? ?? ?????? ??????????? ??????? ???????? ????? ??????? ?????? 723.7? ?????? Laugfs Engineering (Pvt.) Ltd. and Sanken Construction (Pvt.) Ltd. ??? ???????? ????? ????? ???????? ?? ?????????? ??????? ??????? ?????? ??????????? ???????? ???????? ?? ?????? ??????? ?????? ?????? ????? ??? ???.

https://sinhala.news.lk/cabinet-decusions/item/26990-208-01-09

 

CEB-PUCSL dispute overshadows potential power crisis

 

The Power and Renewable Energy Ministry has brushed aside warnings of countrywide power-cuts in March and April due to trade union (TU) action by the Ceylon Electricity Board Engineers’ Union (CEBEU). Deputy Minister Ajith P. Perera told the Sunday Times, he did not believe the CEBEU would resort to a measure as extreme as one that would lead to a countrywide power crisis.

He was speaking in the wake of warnings by the Engineers that power-cuts were possible by March, if their TU action continued into the dry season. TU action has been continuing for some months over a dispute between the CEB and the Public Utilities Commission of Sri Lanka (PUCSL), the power sector regulator, regarding the country’s long term power generation plan.

Engineers have to date kept away from Technical Evaluation Committees (TECs) which handle power purchase tenders. In the latest such development, CEBEU members refused to be part of a TEC appointed to procure 100 Megawatts (MW) of emergency power. Tender for the plant was opened on Friday (12) and will now have to be evaluated by a TEC, before a bidder is selected.

Mr Perera however, was hopeful that such action would not result in a power crisis in the next several months. “There have been occasions in the past where the CEBEU have helped us in times of dire need, even in the midst of TU action. I don’t believe that stance will change.”
The CEBEU held a different view. “If 100 MW emergency power is not available by March, there will definitely be power-cuts, as we can’t expect any rain during this period,” claimed CEBEU Committee Member Athula Wanniarachchi. In case of a breakdown in a major power plant, the situation will be aggravated further. Mr Wanniarachchi insisted the CEBEU was standing firm its members would not take part in TECs for any power procurement project, unless the Government resolves the dispute surrounding the Least Cost Long Term Power Generation Plan (LCLTPGEP).

Several power plants, namely Unit 3 of the Lakvijaya Coal Power Plant in Norochcholai (300 MW), Kelanitissa Combined Cycle Power Plant (160 MW) and Kelanitissa Gas Turbine 7 (100 MW) are also due for shutdowns at different times, from February to April, for routine maintenance. Meanwhile, private power plant Sojitz-Kelanitissa (160 MW) has been out of order from July 2017, due to a mechanical breakdown.

“The combined capacity of all the country’s hydropower reservoirs currently stand at about 68%. Once that level falls to 35%, the situation would be critical, as priority would have to be given to release water for drinking and agricultural purposes,” Mr Wanniarachchi elaborated. “As such, customers, especially industries will suffer.”

“The CEBEU would not take any responsibility if power-cuts do occur,” Mr Wanniarachchi stated, arguing that the Government and PUCSL should take the blame. “We are taking several measures to meet energy needs during the coming dry season, and purchasing emergency power is only one measure,” maintained Deputy Minister Perera, claiming plans are being put in place to avert power-cuts. Meanwhile, the Ministry was working hard to resolve the dispute between the CEB and PUCSL.

Mr Perera also said that, when it came to the country’s long term power generation plan, both the CEBEU and the Ministry are in agreement. That policy envisaged what he claimed was a “correct combination”, which saw a mix of hydro, renewable energy sources and coal among other things.

The problem, he stressed, was due to some officials of the PUCSL who were “clinging firmly to their own opinions.”
“We acknowledge the PUCSL has a right to voice its thoughts. What we are trying to do is narrow down the differences between their opinions and those of the CEB,” he remarked.

Huge Korea-backed project for 1m tons of LNG a year

Experts question Swiss Challenge method for massive annual contract; best price terms cannot be obtained

The Government will open for procurement under the Swiss Challenge method a South Korean proposal for a free-of-charge floating Liquefied Natural Gas (LNG) terminal tied to an annual order of 1mn metric tonnes of LNG for two decades at international market prices–the most expensive tender ever to be floated in Sri Lanka.

But industry and procurement experts insist that any tender for a terminal and for LNG, especially in such vast quantities, must be in keeping with the principles of open international competitive bidding to ensure Sri Lanka gets the best prices and widest participation of global players. They say Swiss Challenge is one of the least-used methods of procurement in the world, a fact well-documented on the internet.

“Credible international bidders are usually reluctant to respond to a Swiss Challenge because it comes on the back of an unsolicited proposal,” said Saliya Wickramasuriya, an independent consultant and former Director General of Petroleum Resources. “They don’t know if it has been informally solicited, and is simply being ‘laundered’ via a Swiss Challenge process.”

A Swiss Challenge usually grants an advantage to the original proposers and often gives them an opportunity to match whatever anybody else tenders. If the structure of the Swiss Challenge is bad, it carries little incentive for serious players to make the effort to compete.
“It is not a competitive process, although it may appear to be,” Mr Wickramasuriya said. “It is not a smart procurement method – typically only used to shift State assets in which few have expressed interest. It is hardly ever used to select partners for strategic projects.

The long-term gas supply to Sri Lanka is a quantifiable, strategic national project. if anything ever was. We don’t need to embark on selecting a partner for that on the basis of one unsolicited proposal.”

The Government should welcome the various unsolicited proposals and “then go to the market with a proper RFP, not a Swiss Challenge,” Mr Wickramasuriya said. “A far better way to handle the high level of interest Sri Lanka’s natural gas market has generated would be to compile a proper tender document, with specific timelines, prices and volumes, and offer it to the entire market place. This way we can compare apples-to-apples, as it were, and avoid the question mark on optimum value addition that Swiss-challenging one particular proposal will inevitably bring,” he said.

A Swiss Challenge is defined as “an offer made by the original proponent to the Government ensuring his process to be the best (in terms of cost and time effectiveness) by his initiative as a result of his own approach or on the demand of the Government to perform a certain task”.
The system allows third parties to make better offers (challenges) for a project during a designated period with a simple objective of discouraging frivolous projects or to avoid exaggerated project development costs in a transparent manner. The original proponent then gets the right to counter-match any superior offers given by the third party.

The bid from the Korean Government-backed SK E&S Company–an integrated gas and power company–was first submitted by President Maithripala Sirisena, according to a letter Power and Energy Ministry Secretary B.M.S. Batagoda sent last month to the Chairman and General Manager of the Ceylon Electricity Board (CEB). The Sunday Times saw a copy of the letter.

A joint memorandum was then put forward by Power and Energy Minister Ranjith Siyambalapitiya and Special Assignments Minister Sarath Amunugama to expedite and request Cabinet approval for the CEB to call the tender based on the Korean proposal under a “Swiss Challenge” concept.

Dr Batagoda said the Cabinet of Ministers has now given approval for the CEB to call tenders for the purchase of LNG for existing power plants and upcoming 300MW power plant based on a Swiss Challenge concept using the Korean proposal. “Since this is (a) new experience for the CEB, we suggest that that the CEB shall create a new unit under the thermal complex to purchase LNG for thermal power plants,” he noted. “The CEB will only purchase LNG. Terminal management structure can be decided separately.”

The Secretary also instructs the CEB management to appoint a Technical Evaluation Committee for the proposal. But the Sunday Times confirmed this week that it has not yet been done, amidst internal fears that the large number of LNG proposals before the Government will lead to “dumping”.

There are at least three separate unsolicited bids for LNG terminals under consideration. The joint Siyambalapitiya-Amunugama cabinet memorandum sought Cabinet approval to call international bids by the CEB for procurement of natural gas for power plants of 1,000mw by adopting the Swiss Challenge procurement method based on the proposal submitted by SK E&S Company backed by the Korean Government.
It also sought approval to invite the Japanese and Indian companies which have submitted proposals for the construction of LNG terminals in Sri Lanka; and the proposed Sri Lanka, India and Japan joint venture company to be established to participate and submit proposals to this tender under Swiss Challenge method collectively or separately.

Finally, the Cabinet has already sanctioned the building of a 400mw LNG power plant and terminal in Hambantota as a combined project by China Machinery Engineering Corporation and the CEB.

The Korean proposal has the suggested starting date for the LNG sale and purchase agreement (SPA) as the second half of 2020, ending on March 31, 2040. The annual contract quantity is specified as either 500,000mt a year or one million mt. The primary sources of LNG will be the seller’s global LNG sourcing portfolio.

The floating storage regasification unit (FSRU) will be provided free-of-charge; the LNG pipeline will be funded by the Sri Lanka Government and, if necessary, SK E&S will provide technology for pipeline engineering, construction and operation. The LNG price is to be at competitive level, “considering that FSRU is free of charge”.

The terms of the contract will be “Take or Pay”: The buyer either takes the product from the supplier or pays the supplier a penalty. The SK E&S proposal says, “If Buyer fails to take any scheduled cargo, Buyer shall pay Seller an amount equal to the Contract Price multiplied by the quantity which Buyer failed to take”.

Kerawalapitiya-II delay could cause Rs 204 B loss

Ceylon Today

By M Rishar M Saleem

Sinister moves by the authorities to sabotage awarding the Kerawalapitiya-ii combined cycle power project to a local company could cause Rs 204 billion in losses to the State, alleged senior engineers of CEB, speaking to Ceylon FT yesterday.
Furthermore, the engineers opined that it was the right of the public to know such moves which affect public life and enormously affect Government coffers. “This would be a much greater scam than the Rs 11 billion Bond scam if it goes unnoticed”, they alleged.
It was brought to light that some authorities with vested interest were favouring the 300 MW Kerawalapitiya-ii combined cycle power plant to be awarded to Samsung Korea, overlooking local bidders whose tariffs were much lower. This is a definite saving of Rs 204 billion to the country; the loss could be 20 times greater than the now-infamous Bond scam.

This scam is now being exposed, thanks to some concerned parties who stand against corruption, whose eyebrows were raised by the fact that Samsung, who was disqualified for non-submission of signed documents for the financial bid was considered a genuine bidder.

Engineers charged that “Despite the scam under the carpet being exposed, players with vested interests lament over fairytales and keep dragging the issue without awarding the contract to the deserving bidder, which is a serious violation of Government tender awarding procedures.” According to sources, the margins between the lowest and second-lowest bidder were no less than a staggering Rs 34 billion, which is three times greater than the Bond Scam losses.

At the beginning of this month, the Director General of the Public Utilities Commission of Sri Lanka (PUCSL), Damitha Kumarasinghe warned that the Kerawalapitiya Liquid Natural Gas (LNG) plant would need to be started soon if they are to keep to the CEB’s timeline of commissioning it by 2019. The PUCSL has repeatedly warned that the country will face an energy crisis soon unless they keep to the approved generation plans and implement what has been proposed.

In this respect, PUCSL officially noted that delaying this essential power plant will certainly cost the country to the tune of Rs 1.55 billion per month when compared to the high cost of short- term emergency power plants required to bridge the gap.
Over the last 20 years, the country has had to resort to diesel and thermal power plants to meet increasing power needs, as the long-term power plants proposed for over 20 years have not materialized in keeping with failures of CEBs project proposals.
The 300MW Kerawalapitiya-II tender was floated by the Ceylon Electricity Board (CEB) as a fast-track power plant, by squeezing the time spans required for each aspect of the project.

Proposals were opened in April 2017 and now a total of eight months have lapsed; the fast-track project has become an off-track project. This delay has already resulted in a loss of Rs 12.4 billion, a figure exactly close to the Bond Scam, unheeded by the public.
The delaying stance adopted by the authorities is questionable as the country faces a severe energy crisis and it is time for the concerned parties to prioritize the country instead of personal gains, the engineers alleged.

Meanwhile, the authorities have issued a drought warning for the March-April 2018 period, which could result in imminent power cuts.

Public Utilities Comm. to be dissolved? Power Ministry to present Cabinet paper soon

Ceylon Today

By Niranjala Ariyawansha

Minister of Power and Renewable Energy Ranjith Siyambalapitiya is to present a Cabinet Paper next week requesting to dissolve the Public Utilities Commission of Sri Lanka (PUCSL) and appoint suitable intellectuals instead, Ceylon Today reliably learns.
According to sources, Ministry Secretary Dr. Suren Batagoda is also preparing to include several negative observations regarding the PUCSL in that particular Cabinet Paper.

He is due to point out that the membership of the PUCSL is not acting professionally and by submitting false figures and statistics in connection with Power Plants, they have misled the public.

They have decided to submit this Cabinet Paper after the PUCSL had last week rejected a Joint Cabinet Paper submitted three weeks ago by Ministers Siyambalapitiya and Dr. Amunugama, saying that a generation mix was required for the energy security of the country.

Simultaneously, this took place within a backdrop where the Least Cost Long Term Generation Expansion Plan (LCLTGEP) 2018-2038 which the CEB had submitted to the PUCSL had been set aside.

This Cabinet Paper had emphasized that, similar to all countries in the world, Sri Lanka too, without depending only on one source of energy to fulfil the future energy needs of the country, should use all other sources including coal.

The LCLTGEP prepared by the CEB states that all energy sources including coal had been mentioned. However, the PUCSL had removed the coal power plants and included many Liquid Natural Gas (LNG) plants instead, pointing out falsely that Coal was far more expensive than LNG, the CEB Engineers’ Union (CEBEU) has alleged.

In a case filed at the Appeal Court by two others including member of the CEBEU Athula Wanniarachchi it has been requested that an order be issued to the PUCSL that the illegally prepared LCLTGEP be withdrawn.

According to the Sri Lanka Electricity Act, No. 20 of 2009, Clause No. 5 and the Public Utilities Commission Act No. 35 of 2002, Clause No. 30, the Subject Minister should prepare the General Policy Guidelines on the Electricity Industry and submit it to the Cabinet. All amendments submitted for these too should be approved by the Cabinet and it should be laid before Parliament and only then be presented to the PUCSL. According to this policy of the government, the LCLTGEP should be prepared by the CEB.

The role of the PUCSL is to regulate whether the CEB complies with implementing the policy provided by the government or not.

Under these circumstances, what the government has done by referring the generation mix policy document prepared by the two ministers, to the PUCSL requesting them to submit their observations is reversing the legal framework that exists. Professor Kumar David, a veteran energy expert and an electrical engineer warns that the government has yet to realize the danger of the ad-hoc decisions they make in the power and energy sector sans any proper policy and as a result Sri Lanka will have to face a severe energy crisis in the near future.

He also emphasized the fact that the beginning of this was the decision taken by the government, to halt the construction of the Sampur Coal Power Plant made without any foresight.

He further told Ceylon Today that even now, the government has set aside preparing an energy policy and instead it is making stupid decisions based on inaccurate guidance of advisors.

By bring to a standstill the Sampur Coal Power Plant a sum of Rs 220 billion would have to be spent to purchase power from high cost diesel power plants and it is a serious mistake, he added.

http://www.ceylontoday.lk/print20170401CT20170630.php?id=38457

If drought hits during March and April CEB engineers warn of power cuts

BY Niranjala Ariyawansha

Ceylon Electricity Board (CEB) engineers have decided not to participate in the technical evaluation process of the 100 megawatt (MW) emergency power tender, which is to be purchased by the Government,……as a solution to face up to the drought conditions which may occur during the months of March and April this year.

Due to this decision taken by the CEB engineers, there could be a strong possibility of power cuts coming into effect during the months of March and April, informed sources informed Ceylon Today.

The tender is to be opened today (12) and the CEB Engineers’ Union (CEBEU) said that the arbitrary conduct of the Public Utilities Commission of Sri Lanka (PUCSL) and the failure of the Government to control the PUCSL, had prompted them to opt out of the evaluation process.

The sources said that during the dry spell even if one unit of the 300MW Norochcholai coal power plant were to breakdown, the situation could become worse.

They added that further complicating the situation would be the third phase of the Norochcholai plant having to be shut down for a 45-day period for scheduled maintenance work and thereby 300MW will be lost to the National Grid during that period.

Though the CEBEU is opposed to the purchase of high cost emergency power, Committee Member of the union, Athula Wanniarachchi said that it was with the greatest displeasure that the tender book, for this tender, had been prepared owing to the failure to build at least one Big Firm Power Plant since 2013.

“But, we are not participating in this tender evaluation. Due to this, during the dry spell, expected in March and April, there is a likelihood of power cuts taking place. If such a scenario is to take place then, the rap for it should be taken by the officers of the PUCSL and those bigwigs of the Government who support such actions,” said Wanniarachchi.

The CEB engineers, upon having completed the technical evaluation process within a fortnight, will need to submit its recommendations to the Technical Evaluation Committee (TEC) which in turn will hand over its recommendations to the Standard Cabinet Appointed Procurement Committee (SCAPC).

The SCAPC will, after having considered the recommendations, award the tender to a suitable bidder.

Due to an ongoing internal battle within the CEB, regarding the Least Cost Long Term Generation Expansion Plan (LCLTGEP), which was filed by the CEB for 2018-2038, the CEBEU had withdrawn its members from the TEC and resorted to trade union action in the past few months.The General Manager of the CEB also had informed the PUCSL that they cannot implement the LCLTGEP compiled by the PUCSL instead of the LCLTGEP compiled by the CEB.

http://www.ceylontoday.lk/article20171001CT20180331.php?id=7265


http://www.ceb.lk/ceb-highlights-serious-errors-in-pucsl-report-on-cost-estimate-for-delays-of-power-projects/

CEB Highlights Serious Errors in PUCSL Report on Cost Estimate for Delays of Power Projects

The Public Utilities Commission of Sri Lanka (PUCSL) has recently released a report titled “Financial Delay in Implementation of Power Plants” which estimates the financial losses due to power plant delays between 2018 to 2020 period at 50.6 billion. CEB had replied to PUCSL stating that the report has over estimated losses by 650% and “has serious calculating errors and major omissions and is prepared without an in-depth analysis”.
This is the second occasion in the recent past where PUCSL had published reports giving figures that carry serious errors as per later CEB findings. In this latest CEB reply, the General Manager CEB had stated that PUCSL’s calculation of the delay to proposed 300MW Kerawalapitiya LNG power plant is a 1300% overestimate. As per CEB calculations the estimated financial losses should be 2 billion and not 28 billion as per PUCSL report. CEB highlighted the major mistakes committed by PUCSL in its estimation, which includes considering the power plant to operate on Liquid Natural Gas (LNG) from 2019 whereas the plant is to be partially operated on Oil in 2019 due to lack of availability of LNG supply infrastructure by then. CEB reply further highlights other mistakes by the commission such as considering the cost of Rooftop Solar as Rs 11.86 per unit whereas the current price paid for a unit of Solar rooftop is Rs 23 per unit. As 60% of current solar additions are from rooftops, such omissions create serious overestimations.
CEB reply also extended CEB assistance to commission staff and states “We accept the need to have an independent, professional regulator and would fully extend our support for your staff to develop such knowledge and skills required. We do acknowledge that electrical power systems is a highly specialized subject area and long years of experience in the fields of power planning and system operations is required to properly understand the intricacies. We cordially invite your staff to develop a close communication with the ministry, CEB and other agencies and understand the practical realities of power plant implementation in the country beyond the ideal, theoretical, isolated world within which they seem to operate.”
The CEB reply concludes by stating “However, if your staff fail to do so, their conduct not only would make timely development of power plant even more difficult to CEB and to the ministry but also would lead to develop a general distrust of reports and figures published by the commission.”

ශ්‍රී ලංකාවේ අනාගත ජනන සංයුතිය තීරණය කිරීම පිළිබඳ ඒකාබද්ධ අමාත්‍ය මණ්ඩල සංදේශය

 

???? ???????? ????? ???????? ????? ?????? ???????? ???? ????? ??????? ??????? ???????????? ??? ??? ?? ?????

??? ????? ?????? ???? ?????? ????? ???????? ?????? ??? ???????? ?????? ????????????? ???????? ???? ?????? ????????? ????? ???? ????? ??????? ?? ???????? ??????? ???? ????????? ???????? ??? ??????? ?????? ????????? ????? ?????? ????? ??????? ??????? ????? ??????, ?? ??? ???????? ????????? ?????? ????? ?????????? ?? ?????? ????? ???? ??????? ??? ?? ??? ?????? ???? ?? ??? ?????? ????? ????.

  • ????? ??? ?????????? ??? ??????? ?????? 14?? ????? ???? ??????? ?????? ????.
  • ??? ??????? ??????????? ?????????? ??????? ???? ????? ???? ????????? ??????  ????
  • ????? ??? ?????? ?? ???? ???????? ??????? ?????? ??????.
  • ?? ??????? ??? ??????? ??????? ??????? ?????? ???
  • ?????????? ?????????? ???? ??? ??????????
  • ???? ?? ???? ??? ???????  ???? ???????? ?? ????? ????????  ??? ???? ????? ???????? 
  • ??????? ????????? ??? ?????? ??? ??????? ??? ????????? ?? ??????? ??????
  • ????? ???? ?? ??? ??? ??? ?????? ?????  ??? ????? ???? ??? ?????? ??? ??????????
  • ???????? COP 21 ???????? ??? ????? ?????? ????? ????? ??????????? ?????? ?? ?????? ????? ????? ??????  ?????? ??????? ?????

CLICK THE IMAGE BELOW TO READ THE LETTER:

thumbnail of Letter to Cabinet Ministers_Signed

Sri Lanka’s LVL Energy Fund starts trading; firm plans to go global

https://www.reuters.com/article/sri-lanka-lvl-energy-fund-listing/sri-lankas-lvl-energy-fund-starts-trading-firm-plans-to-go-global-idUSL4N1P42PD

COLOMBO, Jan 9 (Reuters) – LVL Energy Fund Pvt Ltd debuted higher on the Colombo Stock Exchange on Tuesday after listing a 20 percent stake, and the Sri Lankan energy firm said it plans to expand into Nepal, Bangladesh and East Africa.

A subsidiary of Lanka Ventures Plc and the 298th firm to be listed on the bourse, LVL Energy Fund raised 1.2 billion rupees ($7.81 million) through the listing.

The company will use 720 million rupees for its power projects in Sri Lanka, Bangladesh and Nepal, and the remainder 480 million rupees to service part of its debt.

The company had a debt of more than 700 million rupees, as of March 31, 2017.

The company will start operations in East Africa and also invest in solar power projects as Sri Lanka has shifted its preference towards renewable and LNG power generation from the current thermal, coal and hydro power, K Maheshwaran, acting chief executive officer, told Reuters after the stock’s listing.

“Hydro potentials are getting diminished, so doing any big-size hydro project in Sri Lanka is a dream now,” he added.

“That’s why we have to flow with the wind and go for solar and other external markets such as Bangladesh, Nepal and East Africa to get better returns.”

The company operates five hydro plants, two wind and thermal power plants in Sri Lanka and Bangladesh. It also plans to invest into a 10 MW power plant in Nepal, 1.4 MW and 2.5 MW hydro power plants in Sri Lanka.

Shares of LVL Energy Fund rose as much as 10 percent, before ending up 2 percent at 10.10 rupees a share, compared with the offer price of 10 rupees.